be additional challenges in rescheduling the work postponed in this report, as well as other projects potentially impacted during the 2021 capital budget development.
Financial Matters:
The 2021 road rehabilitation program submitted to Council during the 2020 capital budget deliberations is outlined in the following table.
Items 2, 3, 4, 5, 6, 8 and 9 are to be rescheduled within the upcoming 9-year capital budget plan for 2021 to 2029.
EXISTING 2021 ROAD REHABILITATION PROGRAM | ||||
---|---|---|---|---|
ITEM NO. | STREET | FROM | TO | REHAB. TYPE |
1 | CAMERON AVE | RIVERSIDE DR | CUL-DE-SAC | R/M |
2 | LONGFELLOW AVENUE | ALEXANDRA AVENUE | LABELLE STREET | M |
3 | ALEXANDRA AVENUE | EC ROW | GRAND MARAIS ROAD | M |
4 | ACADEMY DRIVE | EC ROW | GRAND MARAIS ROAD | M |
5 | DANDURAND AVENUE | EC ROW | GRAND MARAIS ROAD | M |
6 | VIRGINIA PARK AVE | EC ROW | GRAND MARAIS ROAD | LIP |
7 | LABELLE STREET | ROCKWELL AVENUE | ALEXANDRA AVENUE | R |
8 | LABELLE STREET | ALEXANDRA AVENUE | DOMINION BOULEVARD | M |
9 | LAUZON PARKWAY | FOREST GLADE DRIVE | TECUMSEH ROAD | PN |
10 | TECUMSEH ROAD EAST | WALKER RD | DROUILLARD RD | R/M |
TOTAL BUDGET | $5,048,000.00 |