GC 5 MATERIAL 

GC 5.01 SUPPLY OF MATERIAL 

All material necessary for the proper completion of the Work, except that listed as being supplied by the Corporation, shall be supplied by the Contractor. The contract prices for the appropriate tender items shall be deemed to include full compensation for the supply of such Material. 

GC 5.02 QUALITY OF MATERIAL

  1. All Material provided by the Contractor shall be new.

  2. Material supplied by the Contractor shall conform to the requirements of the Contract.