- To the intent that the Works shall, at or as soon as practicable after the expiration of the Period of Maintenance, be delivered up to the Corporation in as good and perfect condition, (fair wear and tear excepted) to the satisfaction of the Engineer, as that in which they were at the commencement of the Period of Maintenance, the Contractor shall execute all such work of repair, amendment, reconstruction, rectification and making good of defects, imperfections, shrinkages or other faults, as may be required of the Contractor in writing by the Engineer during the Period of Maintenance, or within fourteen (14) days after its expiration, as a result of an inspection made by, or on behalf of, the Engineer, prior to its expiration.
- iii. All such work shall be carried out by the Contractor at his own expense if the necessity thereof shall, in the opinion of the Engineer, be due to the use of materials or workmanship not in accordance with the Contract, or to neglect or failure on the part of the Contractor to comply with any obligations, expressed or implied on the Contractor's part under the Contract.
- iv. If the Contractor shall fail to commence and proceed diligently to execute any such work as aforesaid required by the Engineer within three (3) days of receipt of notice to do so from the Engineer or the Corporation, the Corporation shall be entitled to carry out such work by its own workers, or by other Contractors, and if such work is work which the Contractor should have carried out at the Contractors own cost, shall be entitled to recover from the Contractor the cost thereof, or may deduct the same from any monies due, or that may become due to the Contractor.
GC 5 MATERIAL
GC 5.01 SUPPLY OF MATERIAL
All material necessary for the proper completion of the Work, except that listed as being supplied by the Corporation, shall be supplied by the Contractor. The contract prices for the appropriate tender items shall be deemed to include full compensation for the supply of such Material.
GC 5.02 QUALITY OF MATERIAL
- All Material provided by the Contractor shall be new.
- Material supplied by the Contractor shall conform to the requirements of the Contract.