- iii. As specified or as requested by the Engineer, the Contractor shall make available for inspection or testing a sample of any Material to be provided by the Contractor.
- iv. The Contractor shall obtain for the Engineer the right to enter upon the premises of the Material manufacturer or supplier to carry out such inspection, sampling and testing as specified or as requested by the Engineer.
- v. The Contractor shall notify the Engineer of the sources of supply sufficiently in advance of the Material shipping dates to enable the Engineer to perform the required inspection, sampling and testing.
- vi. The Corporation will not be responsible for any delays to the Contractor's operations where the Contractor fails to give sufficient advance notice to the Engineer to enable the Engineer to carry out the required inspection, sampling and testing before the scheduled shipping dates.
- vii. The Contractor shall not change the sources of supply of any Material without the written authorization of the Engineer.
- viii. Material which is not specified shall be of quality best suited to the purpose required and the use of such Material shall be subject to the approval of the Engineer.
GC 5.03 REJECTED MATERIAL
Rejected Material shall be removed from the work site expeditiously after the notification to that effect from the Engineer. Where the Contractor fails to comply with such notice the Engineer may cause the rejected Material to be removed from the site and disposed of in what the Engineer considers to be the most appropriate manner and the Contractor shall pay the costs of disposal and the appropriate overhead charges.
GC 6 INSURANCE, PROIECION AND DAMAGE
GC 6.01 PROTECTION OF WORK, PERSONS AND PROPERTY
- The Contractor, the Contractor's agents and all workers employed by or under the control of the Contractor, including sub-contractors shall protect the work, structures, utilities, persons and property from damage or injury. The Contractor shall indemnify, and keep indemnified, the Corporation