against all claims for injuries or damages to any such person, property, structure, utilities, etc.: which may arise out of, or in consequence of, the construction and maintenance of the Works, and against all claims, demands, proceedings, damages, costs, charges and expenses whatsoever, in respect of, or in relation thereto.
- ii. From the commencement to the completion of the Works, the Contractor shall take full responsibility for the care thereof, and in case any damage, loss or injury shall happen to the Works, or to any part thereof, from any cause whatsoever, shall at his own cost, repair and make good the same, so that at completion, the Works shall be in good order and condition, and in conformity in every respect with the requirements of the Contract and the Engineer's instructions. The Contractor shall also be liable for any damage to the work occasioned by him in the course of any operations carried out by him for the purpose of complying with his obligations under Clause 4.21 hereof.
- iii. The Contractor shall assume full responsibility for crossing or making use of private property. Before the Contractor or any of his sub-contractors shall make use of any private property for any purpose, he shall first submit to the Engineer a copy of a written agreement granting permission by the owner.
- iv. The Contractor shall immediately inform the Engineer of all damage and injuries which occur during the term of the Contract.
- v. The Contractor shall not be responsible for loss and damage that occurs as a result of:
- war
- blockades and civil commotions
- errors in the Contract Documents
- acts or omissions of the Corporation, the Engineer, their agents and employees, or others not under the control of the Contractor, but within the Working area with the Engineer's permission.
- vi. The Contractor and his Surety or Sureties will not be released from any term or provision of any responsibility, obligation or liability under the Contract or waive or impair any of the rights of the Corporation except by a release duly executed by the Corporation.
GC 6.02 LIABILITY INSURANCE
- As stated in the General Information to Tenders and prior to any work being commenced in accordance with the Contract, the Contractor shall deliver to the Corporation proof that an insurance policy has been issued