GC 3.04 RIGHT OF THE ENGINEER TO MODIFY METHODS AND EQUIPMENT 

  1. The Contractor shall, when requested in writing, make alterations in the method, equipment or workforce at any time the Engineer considers the Contractor's actions to be unsafe, or damaging to either the Work or existing facilities or the environment.

  2. The Contractor shall alter the sequence of operations on the Contract when requested in writing, so as to avoid interference with other work.

  3. Notwithstanding the foregoing, the Contractor shall ensure that all necessary safety precautions and protection are maintained throughout the Work. 

GC 3.05 ASSIGNMENT AND SUB-LETTING 

  1. The Contractor shall not assign the Contract, or any part thereof, or any benefit or interest therein, or thereunder, without the written consent of the Corporation.

  2. The Contractor shall, at the request of the Engineer, notify the Engineer in writing of the names of the Sub-Contractors proposed for the principal parts of the Work and for such others as the Engineer may direct and shall not employ any to whom the Engineer may object.

  3. If the Engineer should object or refuse to accept any Sub-Contractor or manufacturer's product for inclusion in the Work, he shall not be required