Document/Issue Mitigating Measure/Commitments/Recommendations from EA Implemented(Yes/No) Action SummaryReference Nos. Additions/Exceptions
Healy and Broadway Drain Fisheries DFO Consultation under BSTA - Apr 1 2014
Mitigating Measures to avoid potential serious harm to fish No instream work or construction activity should occur from March 15th to June 30th. Yes AS2  
Work in water should not be conducted at times when flows are elevated due to local rain events, storms or seasonal floods. Yes AS2  
Where riparian vegetation has been damaged or removed, the re-establishmentof grasses / legume vegetation to a like or better condition should be completed.
Yes

AS2, AS8
 
Develop and implement an Erosion and Sediment Control Plan for the site that minimizes risk of sedimentation during all phases of the project. Erosion and sediment control measures should be maintained until all disturbed ground has been permanently stabilized.      
Wash, refuel and service machinery and store fuel and other materials for the machinery in such a way as to prevent any deleterious substances from entering the water within the Broadway Drain, Healy Drain and the Detroit River.
Yes

AS2
 
Develop and implement an Erosion and Sediment Control Plan Installation of effective erosion and sediment control measures before starting work to prevent sediment from entering the water. Yes AS2  
Measures for containing and stabilizing waste material (e.g., dredging spoils) above the high water mark of nearby waterbodies to prevent re-entry. Yes AS2  
Regular inspection and maintenance of erosion and sediment control measures and structures during the course of construction. Yes AS2