3m wide strip measuring 1.5m on either side of the aerial installation (for the length of the alley), as reasonably permitted.
Cogeco Cable Systems Inc. Cogeco will require this easement.
Canada Post Canada Post has no comments for the attached application.
Rogers Communications  
Telus Communications TELUS has no infrastructure in the area of your proposed work. Permit expires six(6) months from approval date.
MNSi MNSi would like an aerial easement through the entire length of the alley closing in question
EnWin Utilities– Hydro Hydro Engineering: No objection, however, an easement named to ENWIN Utilities Ltd. is required for the entire north/south alley upon closing to accommodate existing overhead 16kVand 120/240 volt hydro distribution, poles and down guy wires.
Windsor Utilities– Water Has No Objections
Union Gas/Eldridge Gas I can confirm that Union Gas Limited, now known as Enbridge Gas Inc. does not have any facility located within the proposed closure.
Legal Department It appears that the owner of 1722 Albert is using the alley to access the garage at the rear of the property. The reason for the closure stated on this form includes to prevent “ruts due to car traffic”. This would support the conclusion that the alley is being used. Should the alley or a portion of it be closed: For land abutting properties zoned RD1.3, $1.00 plus deed preparation fee and proportionate share of the survey cost as invoiced to The Corporation of the City of Windsor by an Ontario Land Surveyor.
   
OTHER: