Central Windsor – Basement and Surface Flooding Risk Reduction
Lincoln Road, Ontario Street and Walker Road Storm Sewer Improvements
Recommended Improvements
-
To manage surface flooding under the Climate Change Storm (1:100 year + 40% Factor) on Walker Rd.:
Lincoln Rd. (STM-C17)
-
Construction of 300 m of new storm sewers along Lincoln Rd. between Niagara St. and Cataraqui St.
Ontario St. (STM-C18)
- Construction of 440 m of new storm sewers along Ontario St. between Walker Rd. and Kildare Rd.
Walker Rd.
- Construction of 440 m of new storm sewers along Ontario St. between Walker Rd. and Kildare Rd.
- Enhanced sewer separation of drainage area.
- All Schedule A+ Projects.