SEWER AND COASTAL FLOOD PROTECTION MASTER PLAN
Final Recommendation Summary Report
Downstream Outlet Capacity Improvements
Basement Flooding Solutions
-
- Little River Pollution Control Plant:
-
- Future plant expansion to provide service for population growth and to provide some wet weather treatment capacity.
- In the interim, improve the existing bypass outlet at the treatment plant (Pontiac Pump Station improvements).
- Lou Romano Water Reclamation Plant:
-
- Construct a Retention Treatment Basin Facility and Sandwich Street Combined Relief Trunk Sewer. (Combined Sewer Overflow Control in the Riverfront Area, West of Caron Avenue, Class EA).
Surface Flooding Solutions
Improved or construct new storm sewer outlets to the Detroit River.
-
Detroit St., Bruce Ave., Cameron St., Albert Rd., Marentette Ave.
New or improved stormwater pump station (PS) capacities including emergency back-up power.
-
New St. Rose Ave. PS (St. Rose Park) – New pump station to provide improved outlet capacity and provide relief for significant surface flooding issues.
-
Improve St. Paul PS – Pump Station Expansion to provide relief to drainage area.
-
East Marsh PS – Maintain pump station for a reduced drainage area.
-
Improve Ford Blvd. PS (Reaume Park) – Replace pumps station with larger pump station to improve resiliency of the drainage area.
-
Improve Drouillard PS (Cadillac Park) – Replace existing pump station with new pump station to improve flooding along Drouillard Rd.