Intersection to be removed and the precommitment of these funds established for Strabane project allowing for immediate use of the funds.
These funds will allow for the completion of Tender 105-20.
Based on the above recommendations, there will be sufficient funds in the project to carry out the construction.
Consultations:
Carrie McCrindle – Financial Planning Adminstrator
Melissa Osborne – Senior Manager of Asset Planning
Alex Vucinic – Purchasing Manager
Conclusion:
Administration recommends that transfer of these funds to Project ID 7152000 and award of Tender 105-20 to the low bidder Sherway Contracting (Windsor) Limited.
Planning Act Matters:
Approvals:
Name | Title |
---|---|
Fahd Mikhael | Manager of Design & Development |
France Isabelle-Tunks | Senior Manager City Engineerof Engineering/Deputy |
Mark Winterton | City Engineer |
Shelby Askin Hager | City Solicitor |
Joe Mancina | City Financial Officer / City Treasurer |
Onorio Colucci | Chief Administrative Officer |
Notifications:
Name | Address | |