Recommendation:
The report of the Manager of Energy Initiatives, dated July 16, 2020, related to Energy Initiative projects, BE RECEIVED for information.
Executive Summary:
Background:
This report is intended to provide Council with an update as to the various energy reduction measures implemented throughout the City’s building portfolio.
Discussion:
The Energy Initiatives division of Asset Planning has been engaged in the development and implementation of a number of significant energy efficiency projects. Below is a brief description of projects completed or initiated since 2014 to date.
A – Renewable Energy
1. A 350 kW photovoltaic array was commissioned on the rooftop of the Windsor International Aquatic and Training Center on March 27th 2015 under the provincial Independent Electricity System Operator (IESO) Feed-In-Tariff (FIT) 2.0 Program.
The PV system generates approximately 500,000 kWh of electricity earning the City