Item No. 8.4
Council Report: C 200/2020
Subject: Provincial/Division Corridor Improvements Phase 2 Noise Bylaw Exemption - Ward 9
Reference:
Date to Council: October 19, 2020
Author: Jane Z. He
Engineer III
519 255-6257 ext. 6358
jhe@citywindsor.ca
Design & Development
Design and Development
Report Date: 10/7/2020
Clerk’s File #: SW/13934
To: Mayor and Members of City Council
Recommendation:
I. That the following exemption requests to the provisions of the Noise By-law 6716 (as amended), BE GRANTED to permit for the operation of construction equipment required to complete the trunk storm sewer tunneling through CN Railway:
a. Specific exemption request:
Construction activities during the hours of 8pm through to 6 am, to complete construction of a trunk storm sewer by tunneling through the CN Railway along west side of Provincial Road at Sixth Concession Drain.
b. Scope of Exemption:
The installation of the 2.1-metre in diameter and 70 metres in length trunk storm sewer through CN Railway for the connection of the storm sewer on Provincial Road to the North Roseland Pump Station.
c. Duration of Exemption:
The request is for a period of 30 days with the option for renewal to be approved by the CAO through delegation of authority report.