805.10

BASIS OF PAYMENT

805.10.01

Light-Duty Sediment Barriers - Item 
Light-Duty Straw Bale Barriers - Item
Light-Duty Silt Fence Barriers – Item
Light-Duty Fibre Roll Barriers - Item
Heavy-Duty Sediment Barriers - Item
Heavy-Duty Silt Fence Barriers – Item
Heavy-Duty Wire-Backed Silt Fence Barriers – Item
Berm Barriers - Item
Sandbag Barriers - Item
Fibre Roll Grade Breaks – Item
Flow Check Dams - Item S
traw Bale Flow Check Dams - Item
Fibre Roll Flow Check Dams - Item
Sandbag Flow Check Dams - Item
Rock Flow Check Dams – Item
Sediment Traps - Item
Slope Drains – Item
Diversion Ditches - Item
Sediment Traps for Dewatering – Item
Filter Bags - Item Turbidity Curtains - Item
Cofferdams - Item

Payment at the Contract price for the above tender items shall be full compensation for all labour, Equipment, and Material required to do the work.

Progress payments for the temporary erosion and sediment control measures shall be made as follows:

  1. 30% for initial construction.

  2. 50% for maintenance.

  3. 20% for removal.

805.10.02      Sediment Removal - Item

Payment at the Contract price for the above tender item shall be full compensation for all labour, Equipment, and Material to do the work.

When the Contract Documents do not have a separate item for sediment removal, payment at the Contract price for the appropriate tender item for the installation of the sediment control measures shall be full compensation for all labour, Material, and Equipment to do the work of sediment removal.