805.09 MEASUREMENT FOR PAYMENT
805.09.01 Actual Measurement
805.09.01.01
Light-Duty Sediment Barriers
Light-Duty Straw Bale Barriers
Light-Duty Silt Fence Barriers
Light-Duty Fibre Roll Barriers
Heavy-Duty Sediment Barriers
Heavy-Duty Silt Fence Barriers
Heavy-Duty Wire-Backed Silt Fence Barriers
Berm Barriers
Sandbag Barriers
Fibre Roll Grade Breaks
Measurement shall be the length in lineal metres from end to end of the barrier constructed, maintained, and removed, following the contours of the ground.
805.09.01.02
Flow Check Dams
Straw Bale Flow Check Dams
Fibre Roll Flow Check Dams
Sandbag Flow Check Dams
Rock Flow Check Dams
For measurement purposes, a count shall be made of the flow check dams constructed, maintained, and removed.
805.09.01.03
Sediment Traps
Slope Drains
Diversion Ditches
Sediment Traps for Dewatering
Filter Bags
For measurement purposes, a count shall be made of the number of sediment traps, slope drains, diversion ditches, sediment traps for dewatering and filter bags constructed or installed, maintained, and removed. Component parts shall not be counted separately for payment.
805.09.01.04 Turbidity Curtains
Measurement of turbidity curtain shall be made in lineal metres along its length from end to end between tie-downs for each turbidity curtain installed, maintained, and removed.
805.09.01.05 Cofferdams
For measurement purposes, a count shall be made of the number of cofferdams constructed, maintained, and removed.
805.09.01.06 Sediment Removal
Measurement shall be as specified in the Contract Documents by the volume of sediment excavated in cubic meters or by the number of hours required for excavation of sediment.
805.09.02 Plan Quantity Measurement
When measurement is by Plan Quantity, such measurement shall be based on the units shown in the clauses under Actual Measurement.