Conclusion:
Upon receiving authorization from Council, the Notice of Study Completion will be published in the Windsor Star, on the Project Website, and will be provided to those whom have requested to be included on the project contact list for the EA. The Study Report will be made available on-line on the Project Website.
Planning Act Matters:
N/A
Approvals:
Name | Title |
---|---|
Fahd Mikhael | Manager of Design and Development |
France Isabelle-Tunks | Senior Manager of Engineering / Deputy City Engineer |
Mark Winterton | City Engineer and Corporate LeaderEnvironmental Protection andInfrastructure Services |
Onorio Colucci | Chief Administrative Officer |
Notifications:
Name | Address | |
---|---|---|
Flavio Forest Dillon Consulting | fforest@dillon.ca | |
Distribution list to interested parties submitted to Clerk’s office |
Appendices:
-
Sewer and Coastal Master Plan Executive Summary
-
Draft Notice of Study Completion