c. access to fire hydrants, and water and gas valves located in the working area.

ii. Where any interruptions in the supply of utility services are required and are authorized by the Engineer, the Contractor shall give notice to the affected property owners.

GC 4.06 APPROVALS AND PERMITS

i. The Contractor shall give all notices and pay all fees, required to be given, or paid, by any and all competent and constitutional legislation or any regulation or by-law of any local or other authority in relation to the execution of the Works, or any Temporary Works; and by the rules and regulations of all public bodies and companies whose property or, rights, are, or may be affected in any way by the Works or Temporary Works. The Contractor shall conform in all respects with the provisions of any and all competent and constitutional legislation, and the regulations or by-laws of any local or other authority, which may be applicable to the Works, or any Temporary Works and with such rules and regulations of public bodies and companies as aforesaid, and shall keep the Corporation indemnified against all penalties and liabilities of every kind for breach of any such legislation, regulation, By-law or the Common law as applicable to the Contractor’s Works and duties under this contract.

ii. The Contractor shall pay and arrange for all necessary plumbing and building permits and subsequent inspections.

GC 4.07 EXCESS MATERIALS AND DISPOSAL

i. The Contractor shall remove from the worksite all excess materials including earth and rock excavation, broken concrete, rubble, broken asphalt, tree stumps, etc.

ii. All materials such as metal, wood, asphalt, etc. which are not considered to be “inert fill” as defined in section 18 of regulation 309 under the Environmental Protection Act must be disposed of at waste disposal sites certified by the Ministry of Environment to accept and dispose of these wastes or to sites certified to recycle the waste in question.

GC 4.08 TRAFFIC AND PARKING SIGNS

Prior to commencing work on any street the Contractor shall, with the Engineer and a representative of the Traffic Engineering Department, inspect all signs and ascertain which are to be removed or relocated so as not to interfere with his operations. The Contractor shall then remove or otherwise relocate these signs as directed by the Traffic Engineering Department. Twenty-four (24) hours prior to the completion of any