805.10 805.10.01
BASIS OF PAYMENT
- Light-Duty Silt Fence Barriers – Item
- Heavy-Duty Wire-Backed Silt Fence Barriers – Item
- Berm Barriers - Item
- Fibre Roll Grade Breaks – Item
- Straw Bale Flow Check Dams - Item
- Sandbag Flow Check Dams - Item
- Rock Flow Check Dams – Item
- Slope Drains – Item
- Diversion Ditches - Item
- Sediment Traps for Dewatering – Item
- Filter Bags - Item
- Turbidity Curtains - Item
- Cofferdams - Item
Payment at the Contract price for the above tender items shall be full compensation for all labour, Equipment, and Material required to do the work.
Progress payments for the temporary erosion and sediment control measures shall be made as follows:
a) 30% for initial construction.
b) 50% for maintenance.
c) 20% for removal.
805.10.02 Sediment Removal - Item
Payment at the Contract price for the above tender item shall be full compensation for all labour, Equipment, and Material to do the work.
When the Contract Documents do not have a separate item for sediment removal, payment at the
Contract price for the appropriate tender item for the installation of the sediment control measures shall be full compensation for all labour, Material, and Equipment to do the work of sediment removal.