# Audit report Observation # and name Retargets   Executive approval from Rationale
15 *Facilities Operations 219- Enhance Bi-weekly Management Discussions Original Due Date Dec 31, 2019 Manager, Assets & Projects &Manager, Facility Operations

Background:Internal Audit noted that key workforce metrics (i.e. staff utilization) and commitments on special projects are not formally monitored. Further, tracking, review and coordination of recoverable work is not performed and discussed in management meetings.Management is in agreement that recoverable work orders should be tracked and reviewed. Management will analyze and document the recoverable work process, including how recoverable work will be reviewed.

Reason for Delay: There were 3 key personnel who were required to run daily operations and address the management action plan, however one resigned and another was on unplanned leave. As a result resources were not available to address the issues. The lack of resources, compounded by the COVID-19 pandemic in the first and second quarter of 2020, required a retarget of the due date

Basis for viability of reforecasted: Management personnel positions were available in 2020; however, all focus shifted to providing essential services during the COVID-19 pandemic. If the pandemic concludes by the end of the third quarter of 2020, resources will be assigned to meet the revised target date.