Audit report |
Observation # and name |
Retargets |
|
Executive approval from |
Rationale |
8 |
*Your Quick Gateway (YQG) -Managing Inventory, Repairs and Maintenance |
207 - Enhance key vendor management controls |
Original Due Date |
December 31,2018 |
Chief Executive Officer YQG |
Background: Management has developed a new Purchasing Policy that includes segregation of duties and other vendor management controls (purchasing controls).Reason for Delay: The segregation of duties and related controls are active as of date, however due to the recruitment of a new CEO the Purchasing Policy has been delayed for approval. Director of Finance left corporation on April 3, 2020 and position is currently under recruitment.Basis for viability of reforecasted: Management will be presenting the new Purchasing Policy to the Board before the end of Q2 2020 for discussion and approval. |
Retarget Date |
Dec 31, 2020 |
# of Retargets |
2 |
Days since Identification |
1 year 6 months |
Days past Original Due Date |
365 days |
9 |
Your Quick Gateway (YQG) -Managing Inventory, Repairs and Maintenance |
209 - Enhance compensating controls to address potential segregation ofduties |
Original Due Date |
December 31,2018 |
Chief Executive Officer YQG |
Background: Management has developed a new Purchasing Policy that includes segregation of duties and other vendor management controls (purchasing controls).Reason for Delay: The segregation of duties and related controls are active as of date, however due to the recruitment of a new CEO in Q1 2020, the approval of Purchasing Policy has been delayed. Director of Finance left corporation on April 3, 2020 and position is currently under recruitment.Basis for viability of reforecasted: Management will be presenting the new Purchasing Policy to the Board before the end of Q2 2020 for discussion and approval. |
Retarget Date |
Dec 31, 2020 |
# of Retargets |
2 |
Days since Identification |
1 year 6 months |
Days past Original Due Date |
365 days |
10 |
Managing Transition of Projects into Operations |
211- Enhance project classification and expectation guidelines |
Original Due Date |
Sep 30, 2019 |
Executive Initiatives Coordinator, Office of the CAO |
Background:In a review of the policies, procedures, templates and samples projects, it was noted (a) that project classification requires significant interpretation; and (b) that project management methodologies allow for alternatives but do not include minimum expectations. |
Retarget Date |
Dec 31, 2021 |
# of Retargets |
1 |
|
|
|
|
Reason for Delay: Lack of resources available to carry out the tasks.The Executive Initiatives Coordinator (EIC) in the CAO’s Office has been seconded to the WFM project. This position has not been backfilled and therefore all projects, responsibilities, and duties have been put on hold until its return to the EIC position, the date of which is unknown at this time. |
Days since Identification |
1 year 2 months |
Days past Original Due Date |
92 days |
|
|
|
|
|
|
Basis for viability of reforecasted: The resources for this project are not expected to be available until late 2020/early 2021. From that point they will be required to undertake the management action plan in time to meet the revised date They have capacity set aside at that future time for this work. |