PROJECT CLOSEOUT EVALUATION
PROJECT NAME: | Fire Stations No. 2 and 5 |
---|---|
PROJECT ADMINISTRATORS: |
Fire Station No. 2 Jake Renaud, P.Eng.Wadah Al-Yassiri, P.Eng. Fire Station No. 5 Andrew Dowie, P.Eng. Colleen Middaugh, P.Eng.Jake Renaud, P.Eng. |
DATE: | March 11, 2019 |
BUDGET VS. ACTUAL (bycontract and overall as of XX) | Fire Station No. 2 The project was completed with an overall surplus of XX Fire Station No. 5 The project was completed with an overall surplus of XX |
DEADLINES/SCHEDULE (bycontract and overall) | The projects were originally based on Fire Station No. 7 and the tenders for Fire Stations No. 5 and 2 were originally developed concurrently. The schedules were monitored and confirmed at bi-weekly construction meetings. Fire Station No. 2 PROPOSED SCHEDULE:Contract: December 31, 2014 |