Risk Analysis:

There is a moderate risk to the integrity and reputation of the City for working in good faith with its community partners.

Financial Matters:

City Council already approved $4,310,000 for this project (7162006 - LRWRP Diesel#2Dist Switch Gear) in various iterations of the Capital Budget. Several factors have impacted the total project costs from the original budget estimates and include the following: the participation in the Global Adjustment program, poor soil conditions, changes in the US- Canadian dollar exchange rate, and additional scope requirements for related equipment replacement. Fundiung for the LRWRP Diesel & MCC Upgrade project was approved by City Council as part of the 2011, 2013, 2016 and 2019 Capital Budgets as follows.

YEAR BUDGET APPROVED
   
2011 $1,500,000
2013 $500,000
2016 $500,000
2019 $1,810,000
   
Total $4,310,000

A detailed breakdown of the project’s current financial position and tender costs is provided below:

DESCRIPTION AMOUNT
Consultant (Dillon) - Original $297,500
Consultant (Dillon) – Addendum #1 53,800
Consultant (Dillon) – Addendum #2 62,187
Consultant (Dillon) – Addendum #3 55,800
Construction (Rorison) 3,821,640
Non-Recoverable HST (1.7602%) 75,529