To address the AMANDA related improvement points as part of the 2013 review, the Planning and Development Services Department, at the time of this Internal audit, was undergoing an implementation of the Evolve system, from the vendor, EVOLTA, which is to be completed in August 2020. This system is to replace AMANDA and the SharePoint site in terms of submitting, recording, tracking and managing planning and development related applications for the department. As per management, this system is expected to digitize the application submission and processing phases, which currently are manual across the different types of applications.

Scope

The scope of this internal audit included an assessment of the controls in effect for the period January 1, 2018 through to December 31, 2018.

Internal audit objectives

Overall purpose of this internal audit project was to review controls over the Planning and Development area and to provide insights into the process which may be considered by management in improving the effectiveness, efficiency and economy of current control practices:

Policies and procedures for planning and development

Planning & development application processing

Specific scope exclusions

Given the nature of the work, risk considerations and budgeted effort, the following elements were excluded from the scope of this internal audit: