Meeting Date Motion/ Resolution Report Number CLT Member/ Executive Director Action Status

October 1, 2018

CR550/2018

S 165/2018

Corporate Leader – Parks, Recreation & Culture and Facilities
That the report from Glos Associates Inc. titled “Proposed Relocation/Construction of Lanspeary Park Greenhouse Feasibility Study” and dated September 10, 2018  BE RECEIVED; and further,
That Council  APPROVE OPTION #2 – Construct a new greenhouse complex at Jackson Park- as the preferred solution; and further,
That Council  REFER consideration of the associated funding for the chosen option to the 2019 budget deliberations; and further,
That subject to funding being approved in the Capital Budget, Administration  BE DIRECTED to construct a new greenhouse complex at Jackson Park inclusive of the expansion space for in-house plant production and thereafter proceed to demolish the existing Lanspeary Park Greenhouse Complex, taking into consideration any heritage features or buildings contained thereon, and restore the subject area to parkland; and further,
That Administration  BE DIRECTED to offer options for the expansion of the demonstration house on the site within the re-development plans for Lanspeary Park (options showcasing the low impact re-development); and further,
That Administration  BE DIRECTED to provide information on production numbers for having this in-house versus externally for this service (how much does the taxpayer benefit from having this in-house).
 

October 1, 2018

CR551/2018

S 101/2018

Corporate Leader – Parks, Recreation & Culture and Facilities
That Report S101-2018  BE RECEIVED for information; and,
That Administration  BE DIRECTED to develop plans for constructing municipal single track facilities and for engineered pump tracks at Malden Park and Little River Corridor Park; and,
That Administration  REPORT BACK to City Council with detailed plans incorporating public consultations for the Off-Road Cycle track facilities including cost considerations.