Item No. 8.2

Council Report: S 155/2020

Subject: Wyandotte Street East Corridor Review - Wards 4, 5 & 6

Reference:

Date to Council: December 16, 2020
Author: Jeff Hagan
Transportation Planning Senior Engineer
519-255-6267 ext 6003
jhagan@citywindsor.ca
Planning & Building Services
Report Date: November 17, 2020
Clerk’s File #: APM/9120

To : Mayor and Members of City Council

Recommendation:

THAT report S 155/2020, “Wyandotte Street East Corridor Review,” BE RECEIVED for information.

Executive Summary:

As directed by Council (CR563/2019 & CR265/2020), this report provides information on:

To determine the feasibility of a lane reduction for the identified section of Wyandotte Street East, a corridor review was carried out. The conclusions of the review are as follows: