Appendix ‘F’ – Report S 120/2020
Council Report: S 120/2020
Subject: Close and Convey a Portion of the North/South Alley Between Crawford Avenue and Oak Street, From Montrose Street to Tecumseh Boulevard West and the East/West Alley Between 1370 Oak Street and 1380 Oak Steet - SAA/4133 - Applicants: Richard & Adrienne Chene -
Reference:
Date to Council: September 21, 2020Author: Christopher Aspila MCIP, RPP
Senior Planner - Policy and Special Studies
Phone: 519-255-6543 x6446
Email: caspila@citywindsor.ca
Planning & Building Services
Report Date: September 1, 2020
Clerk’s File #: SAA2020
To: Mayor and Members of City Council
Recommendation:
- XI. THAT the 4.57 metre wide east/west alley located between 1370 Oak Street and 1380 Oak Street, and shown as “Part 1” on Drawing No. CC -1776 attached as Appendix “A”, BE ASSUMED for subsequent closure.
-
XII. THAT the 4.57 metre wide east/west alley located between 1370 Oak Street and 1380 Oak Street, and shown as “Part 1” on Drawing No. CC -1776 attached as Appendix “A”, BE CLOSED AND CONVEYED in equal halves, along the centre of the subject alley, to the abutting property owners, and adjusted as necessary, in a manner deemed appropriate by the City Planner.
-
XIII. THAT Conveyance Cost BE SET as follows:
b. For alley abutting lands zoned Residential RD1.3: $1.00 plus deed preparation fee and proportionate share of the survey costs as invoiced to The Corporation of the City of Windsor by an Ontario Land Surveyor;
-
XIV. THAT the portion of the 2.13 metre wide north/south alley located between Crawford Avenue and Oak Street, from Montrose Street to Tecumseh Boulevard West, and shown as “Part 2”, “Part 3” and “Part 4” on Drawing No. CC -1776 attached as Appendix “A”, BE ASSUMED for subsequent closure.