ENVIRONMENTAL SERVICES – Anne Marie Albidone, June 19, 2020

No concerns from Environmental Services.

ENVIRONMENTAL & SUSTAINABILITY COORDINATOR – Yared Meraal, October 21, 2020

I have no comments in regards to this application.

ENWIN UTILITIES (Hydro Engineering) – Cecile Dalgleish, July 7, 2020

Hydro Engineering: No Objection, provided clearances are achieved and maintained from our distribution plant.

Please note ENWIN has the following distribution around the development property:

  1. overhead 27.6kV primary distribution, 120/240V secondary distribution and underground 120/240V secondary street light distribution along Pioneer Ave on the east side of development property

  2. overhead 27.6kV primary distribution and 120/240V secondary street light distribution along North Talbot Rd on the south side of development property

  3. underground 16.0 kV primary distribution along Sixth Concession Rd on the west side of development property