Transit Windsor has no objections to this development. We currently have our Transway 1C & Ottawa 4 routes servicing the area with the closest bus stops being located on Rivard at Tecumseh. They are approximately 300 metres in distance from this property falling within our 400 metre walking distance average to a bus stop. Our Council approved Transit Master Plan has direct service on Tecumseh in front of this property with 3 different routes servicing this section, which would dramatically decrease the walking distance to a new bus stop. As part of the transit master plan, the existing Transway 1C route will be changed to stay along Tecumseh between Rivard and Roseville Garden. This change was expected to take place in September of 2020, but has been delayed to early 2021 due to the COVID-19 situation.

Jason Scott

Supv, Planning
Transit Windsor
3700 North Service Road East, Windsor, ON, N8W 5X2
Phone: (519) 944-4141x2230

ENWIN Comments

Hydro Engineering: No Objection.

Please note that ENWIN has the following hydro distribution around the property.

  1. Pole line on the south side of Tecumseh in the right of way that includes: overhead primary 27.6kV distribution, overhead secondary distribution both 120/240V and 120/208V, transformer, underground 120/208V secondary conductors

  2. Service to the building is a 120/208V conductor that runs along the western property limit to the pole at the rear and then into the building. 

See attached sketch (below) for reference.

We recommend referring to the Occupational Health and Safety (Ministry of Labour) and Building code to ensure that safe limits of approach and minimum clearance requirements are achieved during and after construction / renovations

Water Engineering: Water Engineering has no objections to the rezoning

Cecile Dalgleish
Technical Services Dispatch
ENWIN Utilities Ltd.