Appendix E
Consultation

The sewers fronting the subject property are a 1200mm concrete storm sewer in the eastbound lane of Tecumseh Road and a 675mm concrete sanitary sewer in the westbound lane of Tecumseh Road. The applicant will be required to obtain a Street Opening Permit for any work within the right-of-way.

In summary, we have no objections to the proposed rezoning and Official Plan amendment.

If you have any further questions or concerns, please contact Shannon Mills, of this department at smills@citywindsor.ca

_____________________________
Patrick Winters, 
Development Engineer

Transportation Planning

Overall, Transportation Planning supports the subject Official Plan and Zoning By-law amendment.

Juan Paramo, P.Eng., Transportation Planning Engineer

Planning and Building Department - Transportation Division

519.255.6267 ext. 6826