APPENDIX E – Draft By-law
B Y - L A W N UM B E R -2020
A BY-LAW TO FURTHER AMEND BY-LAW NUMBER 8600
CITED AS THE "CITY OF WINDSOR ZONING BY-LAW"
Passed the day of , 2020.
WHEREAS it is deemed expedient to further amend By-law Number 8600 of the Council of The Corporation of the City of Windsor, cited as the "City of Windsor Zoning By-law" passed the 31st day of March, 1986, as heretofore amended:
THEREFORE the Council of The Corporation of the City of Windsor enacts as follows:
1. That By-law Number 8600 is further amended by changing the Zoning District Maps or parts thereof referred to in Section 1, of the by-law and made part thereof, so that the zoning district symbol of the lands described in Column 3 shall be changed from that shown in Column 5 to that shown in Column 6:
1. Item Number | 2. Zoning District Map Part | 3. Lands Affected | 4. Official Plan Amendment Number | 5. Zoning Symbol | 6. New Zoning Symbol |
---|---|---|---|---|---|
1 | 11 | Lots 99 to 109; Lots 142 to 152 & Pt closed Alley, RP 1098, designated as PARTS 1 to 3 12R25458, and Lots 16 to 18, 220 to 222, Pt lot 219, Pt closed Alley, RP 1098 (located on the south side of Milloy St, between Meldrum Rd and Chandler Rd) | n/a | RD1.1 | HRD1.2 |
2. That the holding (H) symbol BE REMOVED when the applicant/owner submits an application to remove the H symbol and the following conditions are satisfied:
-
1) General Provisions – The applicant shall conform to the General Provisions of Council Resolutions 233/98 and any other specific requirements. Applicant shall submit proof of the said conformity, to the satisfaction of the City Engineer.
-
2) Servicing Study – Prior to the issuance of a Street opening permit, the applicant shall review the existing and proposed sewer system for this development to determine its effect on the municipal sewer system. The study shall be done to the satisfaction of the City Engineer and the Chief Building Official. The applicant is required to demonstrate that no negative impacts will be realized by the existing surrounding community, before the proposed development will be allowed to proceed.
-
3) Stormwater Management Analysis – The applicant shall complete storm water management analysis to the satisfaction of the City Engineer. Stormwater quality and stormwater quantity shall be addressed up to and including 1:100 year storm event and be in accordance with the guidance provided by the Stormwater Management Planning and Guidance Manual, prepared by the Ministry of the Environment (MOE, 2003) and the “Windsor-Essex Region Stormwater Management Standards Manual”.
-
4) Street Opening Permit – The applicant shall obtain street opening permits for sewer taps, drain taps, road construction, sidewalks, street lights, etc. from the City Engineer, prior to commencement of any construction on the public highway.
-
5) Sidewalks – The applicant shall construct, at its entire expense, according to City of Windsor Standard Specifications and in a manner satisfactory to the City Engineer, a concrete sidewalk along the east side of Meighen Road from Milloy Street to the southerly limit of the Meighen Road extension.
-
6) Meighen Road Cul-De-Sac – The applicant shall construct a cul-de-sac with a minimum radius of 9.5m at the southerly limit of the Meighen Road extension.