Risk Category | Specific Risk | Risk Level | Mitigation |
Timeline Risk | | | -
This risk is not predictable, as the impacts to the timeline are not known until the Archaeological work has commenced. -
Hire an Archaeological Consultant after conceptual design is completed to conclude any required documentation for the area of the plaza. |
| | -
Complete program refining tasks, such as community engagement, as the first task for the consultant. -
Refine conceptual design direction during public engagement process to minimize the need to return to the public for further conceptual direction after the program is adopted. |
| | -
This project has been submitted as part of a larger project grant application. -
The project timelines and milestones are able to adjusted to align with funding programs. The project team has already anticipated this in the schedule to help mitigate the impacts. |
Capital Cost Risks | | | -
Some of the program elements have been defined, but more program elements will be revealed during the Community Engagement and concept design phase for the project. The project will be a Design-Bid-Build delivery so that the entire program will be defined prior to tendering for construction. -
Construction estimates will be provided at major design milestones in order to identify budget issues as early as possible. |