Estimated Costs - Source Control Measures Private and Public Improvements

Private Property Improvements: (Costs are in Millions of $)

Solution Component Central Windsor South Windsor East Windsor Sub-Total Costs
City-wide Foundation Drain and Enhanced Private Property Improvement Program (Note 1) $480.00 $220.00 $250.00 $950.00
City-wide Downspout Disconnection Subsidy Program $15.30 $20.80 $13.70 $49.80
Sub-Total Private Property Source Control Solutions $495.30 $240.80 $263.70 $999.80
Public Infrastructure Improvements: (Costs are in Millions of $)
Solution Component  Central Windsor  South Windsor  East Windsor  Sub-Total Costs
Sanitary Manhole Sealing Program  $0.00  $0.13  $0.35  $0.48
Backflow Prevention Device Program Allowance  $3.50  $0.00  $3.50  $7.00
Sub-Total Public Infrastructure Source Control Solutions $3.50  $0.13 $3.85 $7.48

Notes:

1. An allowance of $20,000 per home held for the implementation of a subsidy program to disconnect foundation drains for older homes.