Pathways of

Effect

Stressor (Potential Impact)

Mitigation Measures

Negative Residual

Effects

   

a minimum of 30 m from the watercourse and temporarily stabilized and/or contained.

 

Uncontrolled release of dewatering effluent from excavation of culvert extension or channel realignment.

Manage dewatering operations from excavation to prevent erosion and/or release of sediment laden contaminated water to Broadway Drain.

Design and use temporary settling basins, filter bags and energy discharge diffusers as required.

No residual effects with implementation of mitigation measures.

Use of Industrial Equipment (B2)

Mobile or stationary equipment may release or leak fuel, oil, grease or other contaminant to the watercourse.

Prohibit/limit access to watercourse/watercourse banks.

Management of spills (spill response plan).

Management of equipment - operate, maintain and store (e.g., refuel, lubricate) all equipment and materials in a manner that prevents entry of any deleterious substances to the watercourse.

No residual effects with implementation of mitigation measures.

Increase erosion potential

Prohibit/limit access to watercourse/watercourse banks.

Design and implement erosion and sediment controls to contain/isolate the construction zone, manage site drainage/runoff and ensure all areas draining to Broadway Drain are stabilized following construction.

Stabilize and revegetate all disturbed flood plain areas

No residual effects with implementation of mitigation measures.