SPECIFICATIONS FOR THE BROADWAY DRAIN IMPROVEMENTS CITY OF WINDSOR

1.0 Genera l

Improvements to the Broadway Drain were completed in conjunction with the Windsor-Detroit Bridge Authority Early Works project designated as Contract No. WDBA 2014-041. Therefore, any reference in this specification to works in the future tense such as “shall” and “shall be” are to be interpreted in the past tense.

2.0 Description of Work

The work to be completed under this Contract consists of the furnishing of all labour, supervision, equipment and materials necessary to carry out the following:

  1. Clearing and grubbing of existing trees and shrubs within the drain and access corridor.
  2. Excavation of new drain.

  3. Filling of the existing drain.

  4. Construction of new steel sheet pile retained channel segment.

  5. Construction of culverts and headwalls.

  6. Construction of Armour Rock Jetty

  7. Restoration including seeding, planting and construction of habitat features.

The above description is general only and must not be considered as limiting the scope of work.

In addition to subsequent sections of these specifications, reference is made to applicable sections of Book I – Part 5, and Books II, III, IV, V, VI, VIII and X of the Contract No. WDBA 2014-0041, applicable OPSS Forms and City of Windsor Standard Specifications. OPSS Forms can be accessed at:

http://www.raqsb.mto.gov.on.ca/techpubs/ops.nsf/OPSHomepage

Applicable sections of the City of Windsor Standard Specifications can be accessed at:

https://www.citywindsor.ca/business/buildersanddevelopers/Pages/Standard-Specifications.aspx