185.07.11.02      Removal of a Temporary Flow Control Within a Waterbody

As a minimum, temporary flow control within a waterbody shall be removed according to the following sequential steps:

  1. All Work in the Working Area shall be completed and the original waterbody channel, isolated by the temporary flow control, shall be stabilized in accordance with the Contractor’s design prior to returning the flow of water to the original waterbody channel.

  2. The downstream plug shall be removed.

  3. The upstream plug shall be removed.

  4. The temporary flow control shall be removed.

185.07.12          Management of Excess Material

Management of excess material shall be according to the Contract Documents.

185.10         BASIS OF PAYMENT

Payment at the Contract price for the appropriate tender items that require temporary flow control shall include full compensation for all labour, Equipment, and Material to do the work.

When the Contract contains separate items for work required by this specification, payment shall be at the Contract prices and according to the specifications for such work.