8.5 Landscape and Restoration Works
Item Description | Cost |
---|---|
a) Supply, place and final grade topsoil | $67,278.75 |
b) Supply and place seed and mulch | $38,547.27 |
c) Supply and place erosion control blankets along south slope | $15,712.51 |
d) Supply and plant Trees | $50,805.42 |
e) Supply and plant Shrubs | $14,414.60 |
f) Supply and plant perennials and ornamental grasses | $16,071.64 |
g) Supply and plant aquatic plants | $5,498.00 |
h) Supply and place hardwood mulch | $6,087.37 |
Landscape and Restoration Subtotal | = $ 214,415.56 |
8.6 Habitat Features
Item Description | Cost |
---|---|
a) Salvage and stockpile root balls | $3,780.00 |
b) Supply and place armour rock vanes | $53,925.32 |
c) Construct 3 snake hibernacula | $16,215.00 |
d) Place salvaged root balls | $2,760.00 |
e) Supply and place armour rock clusters | $16,665.60 |
f) Supply and place field stone clusters along channel | $13,240.80 |
Habitat Features Subtotal | = $ 106,586.72 |
8.7 Miscellaneous Works
Item Description | Cost |
---|---|
a) Implement and maintain sediment and erosion control | $68,900.00 |
b) Install clay cut-off trench | $174,085.40 |
c) Fish salvaging | $7,500.00 |
d) Temporary culvert to access south side of the drain | $26,050.00 |
Miscellaneous Works Subtotal = $ 276,535.40 | |
SUB-TOTAL CONSTRUCTION COST……….. $ 3,448,848.04 |