Minutes City Council Monday, February 03, 2020

August 1, 2019 

JUSTINA NWAESEI PLANNER CITY OF WINDSOR 350 CITY HALL SQUARE W, SUITE 320 WINDSOR ON N9A 6S1 

Reference: ZNG-013/19 [ZNG/5875] AND SDN-003/19 [SDN/5831]

Dear Justina,

Thank you for contacting Canada Post regarding plans for a new development in the City of Windsor. Please see Canada Post’s feedback regarding the proposal, below.

Service type and location

  1. Canada Post will provide mail delivery service to the subdivision through centralized Community Mail Boxes (CMBs).

  2. If the development includes plans for (a) multi-unit building(s) with a common indoor entrance, the developer must supply, install and maintain the mail delivery equipment within these buildings to Canada Post’s specifications.

Municipal requirements

  1. Please update our office if the project description changes so that we may determine the impact (if any).

  2. Should this subdivision application be approved, please provide notification of the new civic addresses as soon as possible.

Developer timeline and installation

  1. Please provide Canada Post with the excavation date for the first foundation/first phase as well as the date development work is scheduled to begin. Finally, please provide the expected installation date(s) for the CMB(s).

Please see Appendix A for any additional requirements for this developer.