contract or termination of the Contractor's right to continue with the work in whole or in part shall continue to be in force after such termination. 

GC 4 CONTRACTOR'S RESPONSIBILITIES AND CONTROL OF THE WORK

GC 4.01 GENERAL 

  1. The Contractor shall have complete control of the work and shall effectively direct and supervise the work, to the satisfaction of the Engineer, so as to ensure conformity with the contract documents. The Contractor shall be responsible for construction means, methods, techniques, sequences and procedures and for coordinating various parts of the work.

  2. The Contractor shall comply with and adhere strictly to, the Engineer's instructions and directions on any matter (whether mentioned in the contract or not). The Contractor shall take instructions and directions from the Engineer.

  3. The Contractor shall have the sole responsibility for the design, erection, operation, maintenance and removal of temporary structures and other temporary facilities and the design and execution of construction methods required in their use.

  4. Notwithstanding paragraph iii of subsection 4.01, where the Contract Documents include designs for temporary structures and other temporary facilities or specify a method of construction in whole or part, such facilities and methods shall be considered to be part of the design or the specified method of construction. The Contractor shall, however, be responsible for the execution of such design or specified method of construction in the same manner that the Contractor is responsible for the execution of the Work.

  5. The Contractor shall be responsible for construction health and safety within the working areas and for compliance with the current Occupational Health and Safety Act and Regulations and the current Workers Compensation Act. So as to avoid any misunderstanding as to the extent of the Contractor's responsibility, the Contractor, by executing the Contract unequivocally acknowledges that the Contractor is the Constructor within the meaning of the Act.

  6. The Contractor shall be required to submit a progress schedule to the Engineer for approval prior to commencement of the work. Such