vi. If the Corporation terminates the Contractor’s right to continue with the work in whole or in part, the Corporation will be entitled to:

vii. If the Corporation’s cost to correct and complete the work in whole or in part is less than the amount withheld from the Contractor the Corporation will pay the balance to the Contractor as soon as the final accounting for the contract is complete.

viii. The Contractor’s obligation under the contract as to quality, correction and warranty of the work performed prior to the time of termination of the contract or termination of the Contractor’s right to continue with the work in whole or in part shall continue to be in force after such termination.


GC 4 CONTRACTOR’S RESPONSIBILITIES AND CONTROL OF THE WORK

GC 4.01 GENERAL

i.

The Contractor shall have complete control of the work and shall effectively direct and supervise the work, to the satisfaction of the Engineer, so as to ensure conformity with the contract documents. The Contractor shall be responsible for construction means, methods,