METRIC OPSS 805 NOVEMBER 2015
CONSTRUCTION SPECIFICATION FOR TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES
TABLE OF CONTENTS
- 805.01 SCOPE
- 805.02 REFERENCES
- 805.03 DEFINITIONS
- 805.04 DESIGN AND SUBMISSION REQUIREMENTS - Not Used
- 805.05 MATERIALS 805.06 EQUIPMENT - Not Used
- 805.07 CONSTRUCTION
- 805.08 QUALITY ASSURANCE - Not Used
- 805.09 MEASUREMENT FOR PAYMENT
- 805.10 BASIS OF PAYMENT
APPENDICES
805-A Commentary
805-A Commentary
805.01 SCOPE
805.01 SCOPE
This specification describes the requirements for the installation, maintenance, and removal of temporary erosion and sediment control measures.
805.01.01 Specification Significance and Use
This specification has been developed for use in provincial- and municipal-oriented Contracts. The administration, testing, and payment policies, procedures, and practices reflected in this specification correspond to those used by many municipalities and the Ontario Ministry of Transportation.
Use of this specification or any other specification shall be according to the Contract Documents.