Class 3: Investments with components of both Sustainability and Enhancement


Project Number

Project Title

Major Category

Project Detail Page #
Economic Development, Growth, and Service Enhancements
Service Sustainability Investments %

2020

2021

2022

2023

2024

2025

2026

2027

Total
ECP-022-07 Prince Rd./Totten St. Storm Sewer Improvements - Engineering & Construction Sewers 334 20% 80% 80,000 - 100,000 - 2,450,000 2,250,000 - - 4,880,000
ENG-003-13 Sixth Concession Municipal Drain - Land Acquisition & Capital Improvements Sewers 351 50% 50% 500,000 200,000 535,000 485,000 - - - - 1,720,000
OPS-008-20 Traffic Signal Upgrades and Replacements Transportation Infrastructure 479 50% 50% 1,294,475 1,271,208 1,147,940 804,673 1,721,405 2,278,137 2,930,000 2,330,000 13,777,838
OPS-009-07 Transportation Planning Environmental Study Reports (ESRs) Transportation Infrastructure 559 20% 80% 100,000 225,000 100,000 100,000 100,000 100,000 100,000 - 825,000
Total Class 3: Investments with components of both Sustainability and Enhancement 11,735,775 12,660,988 10,63666,440 3,889,673 23,466,645 30,181,417 34,412,000 29,115,000 156,097,938